[Koha] Change due date for early renewal
Chris Cormack
chris at bigballofwax.co.nz
Thu Mar 6 15:51:25 NZDT 2014
On 6 March 2014 15:44, Bengal Library Association <blacal.org at gmail.com> wrote:
> If any user renews an issued item before due date koha shows due date
> calculated on the basis of the 1st issue date not on the basis of renewal
> date. What is the solution?
>From the manual
Go to systempreferences, go to circulation
Then change
RenewalPeriodBase
(Koha will do what you tell it to do, in this case you must have the
systempreference set to the old due date of the checkout, change it to
be the current date)
Chris
More information about the Koha